代做C19PT Project Management Coursework Two- Individual Assignment代写数据结构程序

C19PT Project Management Coursework Two- Individual Assignment

Contemporary Issues in Project Management: the Eco-Upgrade 2025” Project Case

(worth 60% of overall course grade)

Submission:

Submission Deadline: before 12:00 pm (UK time) via submission box on Canvas

Assignment submitted within 5 working days after this deadline will lose 30% of the final

mark. Submission is locked after 5 working days with zero marks.

You will receive the mark and feedback 3 weeks after the submission date.

1) INTRODUCTION

This coursework introduces a realistic, industry-based project management scenario developed in collaboration with Siemens LLC Dubai. The case study, titled “Eco-Upgrade 2025” is derived from an actual multi-site infrastructure upgrade project, designed to illustrate the complexity of managing large- scale, sustainability-focused engineering programmes under tight constraints to deliver against a demanding, quantifiable outcome.

You are tasked to draft a report on the planning of the Execution phase of this project, providing Project Charter, Work Breakdown Structure (WBS), Cost Breakdown Structure (CBS), Gantt Chart, Risk Register, and Project Launch Plan based on the information provided.

2) PROJECT OVERVIEW

The Eco-Upgrade 2025 initiative originated from the Pinnacle Horizon Development group; a major real estate owner committed to enhancing the operational efficiency of its multi-site commercial portfolio. Recognising the need for specialized expertise in large-scale system integration, Pinnacle Horizon partnered with Siemens, who took on the role of the primary contractor and system integrator. This organisational structure—client (Pinnacle Horizon) overseeing contractor (Siemens) for an immense, multi-site  retrofit—immediately established a complex project environment focused on balancing aggressive sustainability targets with the operational realities of ten continuously occupied buildings.

The contract awarded to Siemens for the Pinnacle Horizon Development, formally titled “Eco- Upgrade 2025”, represented a critical commitment to sustainability, classified as a challenging Large-Scale Infrastructure Upgrade & IT Migration. The fundamental objective of the initiative was both ambitious and non-negotiable: to achieve a minimum 15% reduction in annual energy consumption across the ten major buildings targeted within the real estate portfolio.

This energy target established the ultimate metric of success, against which the entire investment would be measured. Financially, the project was scaled at AED 10 million in total, with AED 7.1 million specifically ring-fenced for the intensive Execution Phase, the core period under detailed operational scrutiny.

3) PROJECT SCOPE

To achieve the stringent 15% reduction goal, the comprehensive scope was structured around three highly interdependent technical workstreams.

•    The most significant engineering challenge involved the Chiller Heart Transplants, requiring the replacement of one old, inefficient chiller unit in each of the ten buildings. This task demanded heavy logistical coordination, critical timing, and meticulous compliance with local Regulatory Compliance and building codes.

•    Simultaneously, a vast Lighting Overhaul was required, necessitating the retrofit of 5,000 conventional lighting fixtures across the sites with modern, energy-efficient LED technology.

•    Finally, the Smart Brain component provided the future-proofing layer, involving the installation of 400 energy-control sensors coupled with centralized equipment control software designed to optimize system performance dynamically, thus ensuring sustained efficiency post-launch.

The success of the Execution Phase was anchored to three Major Milestones:

•    the physical Materials Delivery of specialised components like the chillers and LEDs.

•    the successful completion of the installation and software deployment, marking Go-Live.

•    and the ultimate validation  point, which was the Final Handover following a rigorous 3-Month Energy Audit to confirm the 15% energy reduction target had been met.

However, the mission was immediately constrained by an aggressive 6-month timeline for the Execution Phase, leaving zero room  for schedule slippage. This timeline was further compounded by severe operational friction, as the buildings remained  fully occupied, enforcing strict Access  limitations that mandated scheduling much of the intrusive work—like core drilling for sensors or crane access for chillers during off-peak hours, significantly increasing logistical complexity.

4) PROJECT RISK

The project manager identified three primary risks that threatened this precarious schedule:

Firstly, the team faced  potential Supply Chain Delays for the specialised,  long-lead-time chiller units.

Secondly, the large-scale nature of the installation work, the 5,000 lights and 400 sensors created a high probability of Occupant Disruption.

Finally, the critical technical risk was the possibility of Integration Failure, where the new control sensors and software might not communicate correctly with the diverse, pre-existing building IT network.

5) PROJECT LAUNCH & HANDOVER

Crucial to moving the project from construction to daily operation was the structured Launch and Handover Plan. The official Formal Handover was set up with a checklist. This required the Operations team to sign off on all technical paperwork, including operations & maintenance (O&M) manuals and final technical drawings (as-built drawings).

The last step was the legal transfer of manufacturer warranties for the new equipment and a final Acceptance Sign-off by the Facility Manager. At the same time, a strong Training Plan was used. It followed a Train-the-Trainer model to teach the Facility Management team how to use the new control software. Training was specifically targeted at Maintenance Technicians (detailed operations) and Facility Managers (high-level reporting). This transition was supported by a dedicated 2-week post-launch support hotline from the vendor.

Finally, a Marketing and Communication effort was planned to manage the change. This included an internal announcement from the CEO/CFO via email about the successful upgrade and expected annual cost savings, and a success story presentation for the Board focused on sustainability.  Key Publicity Material was created for the tenants, including an internal website FAQ about the new smart controls and a digital "User Guidance Flyer" (e.g., how tenants should report a light or temperature issue).

6) MORE DETAILED INFORMATION ABOUT THE PROJECT

Work Breakdown Structure:

The WBS is structured to the Work Package level for the chosen Execution Phase.

WBS Level       Deliverable / Work Package Name

1.0                   Execution Phase

1.1                   Chiller Replacement (10 Units)

1.1.1                Chiller Decommissioning & Removal (per site)

1.1.2                 New Chiller Installation & Piping (per site)

1.1.3                 Chiller Start-up & Initial Testing (per site)

1.2                    LED Lighting Retrofit (10,000 Fixtures)

1.2.1                 Pre-Installation Circuit Mapping (per site)

1.2.2                 Conventional Light Removal

1.2.3                 LED Fixture Installation

1.2.4                 Area Lighting Quality Verification

1.3                    Smart Controls System Installation (400 Sensors)

1.3.1                  Sensor Mounting & Cabling (per site)

1.3.2                  Equipment Control Software Configuration (Central)

1.3.3                  System Integration Testing (Chillers & Lights to Software)

1.4                     Site & Project Closure

1.4.1                  Final Site Clean-up & Waste Disposal

1.4.2                  Phase Go/No-Go Decision & Sign-of

Cost Breakdown Structure (CBS) & Budget Allocation

The CBS maps the high-level budget structure to the WBS deliverables for the Execution Phase. This is a partial view, focusing on the execution portion of the total AED 10M budget.

CBS Item (Mapped to WBS) Budget Allocation (Execution Phase)

1.1 Chiller Replacement                                         AED 4,500,000

Labor (Heavy Equipment, HVAC Technicians)           AED1,500,000

Equipment/Materials (Chillers, Piping, Cranes)          AED 3,000,000

1.2 LED Lighting Retrofit                                        AED1,500,000

Labor (Electricians, Clean-up)                                 AED 500,000

Equipment/Materials (LED Fixtures, Ballasts)            AED 1,000,000

1.3 Smart Controls System Installation                    AED 1,000,000

Labor (IT/Controls Engineers, Installers)                  AED 400,000

Equipment/Materials (Sensors, Software Licenses)    AED 600,000

1.4 Site & Project Closure                                       AED100,000

Total Execution Phase Budget                                 AED 7,100,000

Project Scheduling and Dependencies (Activities)

The following key activities detail the sequencing and duration required for a Critical Path Method (CPM) analysis and Gantt Chart design. Durations are expressed in Days for this project.

Activity ID

Activity Name

Duration (Days)

Preceding Activities (IDs)

A

Complete Site-Specific Safety & Access Permits (All 10 Bldgs)

14

-

B

Execute Chiller Replacement in First 5 Buildings (Group 1)

56

A

C

Execute LED Retrofit in First 5 Buildings (Group 1)

42

A

D

Integrate & Test Sensors in First 5 Buildings

21

C

E

Execute Chiller Replacement in Remaining 5 Buildings (Group 2)

56

B

F

Execute LED Retrofit in Remaining 5 Buildings (Group 2)

42

C

G

Integrate & Test Sensors in Remaining 5 Buildings

21

F

H

Full System Integration Test (All 10 Buildings)

14

D, G

I

Final Site Inspections & Documentation Handover

7

E, H

J

Phase Go/No-Go Decision

7

I

7) CONTENT OF THE PROJECT REPORT

You are required to analyse the Siemens Eco-Upgrade 2025 case and produce a professional project management report that demonstrates your ability to plan and control a complex engineering project. Your work should be developed from the information provided in the case study, supported by independent research and relevant academic literature. Your submission must include the following components:

1.    Executive Summary

2.    Introduction

3.    Project Charter

A concise summary of the project’s purpose, objectives, scope, success factors, available resources, milestones, risks, and approval signatures.

4. Work Breakdown Structure (WBS)

A structured WBS down to the work package level for the execution phase

5.    Cost Breakdown Structure (CBS)

A detailed cost allocation mapped to the WBS, illustrating how the AED 7.1 million Execution Phase budget is distributed

6.    Project Scheduling

A Gantt chart demonstrating the critical path, showing dependencies, sequence of activities, durations and milestones. Note that the milestones are indicated from the project case story itself and it was not included in the list of activities table.

7.    Risk Management

Identify risks that might affect the project execution phase, categorise them in a Risk Breakdown Structure (RBS), and assess their probability and impact using a Probability/Impact Matrices. Finally, summarise this information in a Project Risk Register that list out the risk owner and responses to be implemented. Clearly state how your responses would address the three primary risks that threatened the precarious schedule in the main text. Use academic references to support your arguments.

8.    Project Launch Plan

A structured Completion Checklist outlining items that need to be completed or modified before the project transitions from implementation to operational use, focusing on:

•    Handover procedures

•    Training strategy

•    Internal and external communication and marketing

•    Publicity and stakeholder engagement materials

9. Conclusion

10. Reference list

11. Annexures

8) GENERAL SUBMISSION GUIDELINES

The submission deadline of CW2 is on 12:00 UK time.

•    This report is to be 2500 words (+/- 10%) excluding reference list, tables, figures and annexures.

•    Must contain a minimum of 5 academic references, excluding company/project/newspaper/magazines/web page references.

•    Formatting style should be ‘Arial’, 12pt and 1.5 line spacing. The language must be third person, formal, presented in an academic style.

•    Title/Cover page: You must include a title/cover page that includes: your student ID, module code, assignment title, word count.

•    Use of GenAI: This assessment permits the use of GenAI but ONLY on GenAI-assisted presentation, and GenAI-assisted editing and proofreading, ONLY if they are clearly

referenced and noted in the submitted work. Detailed guidelines of how to reference them please refer to Canvas.

•    Submission of CW2: A properly formatted Word file of your coursework MUST be

submitted to the correct Turnitin link (via the Assessment area on Canvas). No hard copy of your work is required even if you are based on campus. We do not accept submission through emails.

•    Late submissions: In line with University Policy, any work submitted after the set date

and time will automatically have a penalty applied. The penalty is a reduction by 30% of the mark awarded. Submission will be accepted up to five working days after the

submission deadline - your work will be marked, the late penalty applied, and you will receive feedback. Coursework submitted after five working days will be awarded NO grade and you will not be entitled to feedback.

•    Extensions. No extensions for coursework are permitted unless an extension is given to the whole class (in exceptional circumstances). The course leader cannot grant

individual extensions. If you foresee having issues submitting by the deadline, please contact your Personal Tutor and apply for Mitigating Circumstances (MC)




热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图