Assessment Brief

Purpose of an assessment brief

(How should I use this brief to help with my assessment?)

This brief gives you key information and guidance about your assessment. It’s the starting point for your work, and your module tutors will refer to it during assessment discussions. Read the brief carefully, along with any other materials your tutors provide, and use them to help you plan and complete your assessment.

1.0 Essential Information

Module Code and Title

EC2CQC Construction Quantification and Costing

Assessment Title

Coursework 2 – Take-off and Bill of Quantities preparation

Assessment weighting

70%

Submission Date and Time

01/12/2025; 12 noon

Word Count/Page Count/Lengths of presentation/ Fixed Window

Assessment Period (in hours/days)

N/A

2.0 Assessment Overview

Assessment Mode (What do I need to produce at the end?)

You will produce a take-off, priced bill of quantities and supporting report on how the bill has been priced.

Task Description (What do I have to do for this assessment?)

Your client, Moatkeep Developments, has made the decision to proceed with this proposed residential development. The project is now at RIBA stage 4, and a design consultant has produced designs and specifications for the different house types.

· As the consultants with responsibility for providing cost advice to the client, CQC Consult must prepare a Bill of Quantities (BoQ) for the scheme to send out to contractors to tender for the works. As a member of the team, you are required to take off quantities and prepare a BoQ in accordance with NRM2 for Plot 1 ONLY (Appendix A).

NOTE 1: Measure the following building works ONLY: substructure, external walls, internal walls, roof and internal finishes (ceiling, wall and floor).

NOTE 2: You are not required to take off quantities for doors and windows, floors and stairs, electrical services, gas installation, water supply and drainage, bathroom and kitchen fittings as these will be carried out by the respective sub-consultant organisations. However, include these items in the BoQ as Prime Cost (PC) Sums. Include also a Preliminaries section, Dayworks section and Contingency section in your BoQ and a Summary page at the end.

NOTE 3: You are required to make reasonable assumptions for any information not provided in the specifications or drawings. Any assumptions made should be reported in a query sheet. Your submission should include a take-off list, query sheet, take-off, abstract sheet and the BoQ.

· Price all the items in your BoQ using rates you have calculated from first principles and rates from price books such as Spon’s, Laxton’s, Wessex, Hutchins, BCIS, or any other referenced source.

The following additional information is provided to you:

Allow 20% for main contractor’s overheads (O/Hs) and profit

Determine the construction duration for the Pembroke house type alone and use this in pricing your preliminaries

Nominated subcontractors will execute all the works that were not measured. Allow the following Prime Cost (PC) Sums in the BoQ in respect of these works:

Item

Prime Cost (PC) Sum

Upper floor and stairs

£10,400

Windows and external doors

£13,000

Internal doors

£7,500

Sanitary fittings and Kitchen fittings

£12,000

Water supply and drainage

£10,000

Electrical services

£9,500

Gas installation

£8,650

Add 7% as the contingency sum.

Your submission should include a summary report explaining the pricing process and any assumptions made. The report should be a maximum of 300 words. Show clearly what cost information has been used, and how such cost information has been adjusted. All sources of information should be clearly identified and referenced.

Submission Instructions (When and Where do I submit?)

Please submit your assessment via your module’s Assessment Area on CloudCampus.

Preferred Format

· Style. PDF of Take-off and BoQ to professional standards, and report on pricing methodology (plus any native file e.g., MS Excel, Costx submitted as separate file for checking).

· Document Title: Student number_EC2CQC_BoQ

· Word Count: Not applicable

· Preferred reference style. Harvard referencing

3.0 Purpose of Assessment

Link to Learning Outcomes (How does the assessment help you demonstrate the outcomes of this module?)

Coursework 2 requires students to measure a building in accordance with NRM2, prepare a bill of quantities and price the bill of quantities. This course work helps you to achieve LO2 and LO3 of the module as it introduces you to the RICS’s New Rules of Measurement Book 2 (NRM2), how to measure for the purposes of preparing a bill of quantities, and how to price measured items.

Purpose of Assessment (Why am I doing this? How does this link to my future role as an professional in the discipline? What knowledge, concepts or skills should I demonstrate? How might this links to (name of specific PSRB?) )

The rationale behind this task is to provide an opportunity for you to develop competency in the quantification and costing of construction works which are all core competencies of the RICS required to be demonstrated at Level 3 (Being able to give strategic and reasoned advice, including the preparation and presentation of reports with reference to cost).

The CIOB similarly requires professional Construction Managers to be able to produce examples of price and cost estimation for construction activities from feasibility through to final accounts, and produce detailed measurement using a range of standard methods of measurement. They must be able to apply professional standards of reporting and accountancy and demonstrate understanding of the need for honesty and accuracy in reporting. The knowledge, skills and experience needed to showcase these attributes are developed through this assessment.




热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图