代做48360 Geotechnical Engineering调试SPSS

48360

Geotechnical Engineering

Design Project

DESIGN PROJECT

INTRODUCTION

It is important to note that this design project is a group task, with each group comprised of two members.

A company is planning to undertake a construction project on land formerly used as a storage area for a petrochemical factory. You have been tasked with assessing certain geotechnical aspects of this project.

This project presents an open-ended problem-solving challenge, necessitating the application of proper engineering assumptions based on common sense, engineering principles, and some research.

PROJECT DESCRIPTION

The development involves the construction of three retaining structures (north, east and west), an earth batter wall (south), a proposed building, a proposed car park and a steel water tank.

The project in particular consists of construction of:

· A concrete walled industrial building with plan dimensions of 16 m × 40 m. The building is to have an on-ground concrete floor slab 120 mm thick, with a finished RL of 13.80 m. The walls are load bearing and there are some internal columns carrying the weight of the roof and other elements.

· A steel water tank having an external diameter of 12 m and an effective height of 8.5m, with its base at RL 18 m (top of the circular concrete footing). 

· The weight of a large water tank (made of metal) could be around 1.5% to 3% of the weight of water inside the tank (i.e. total water capacity).

· The weight of the circular concrete footing would be around 5% to 8% of the weight of water in the tank with its full capacity.

· Pressure of water can be calculated based on the height of water in the tank. The water pressures factor for stability analysis is equal to one. The pressure due the weight of the empty tank plus its circular foundation would be between 8 kPa and 12 kPa.

· Other assumptions are welcome and can be accepted with simple justifications.

· There is an existing one-storey double brick building on the site. The RL of the slab on the ground is 17.6 m (top of the slab).

A “Site Plan” is attached, showing the location of the tank, the car park (RL 17.5 m, finished surfacing) the proposed and existing buildings. The southern area of this site will act as the access point during construction. This access point will permit vehicle, machinery and temporary pedestrian access, as well as the delivery of tools, equipment and construction supplies. As a result, this area will undergo change at multiple stages of the project, and the landscape will not reach its final state until the project approaches completion. To create a homogeneous earth structure and ensure confidence in the batter design, only one of the sand types found on site will be used to reconstruct the earth batter. The light brown sand located in the fourth layer of this site has been selected because it is readily available. A sufficient quantity of this sand will have to be stored on site during the bulk excavation of the lower level, prior to reconstruction the sand stockpile will have to be conditioned and hydrated to ensure that 95% of standard compaction can be achieved.  

The structural engineer for the project has determined the proposed building loads and they are as follows:

· Wall vertical loading per meter run (including the weight of foundation): 150 kN/m

· Wall moment per meter run (towards inside the building): 70 kN m

· Total load of each column (including the weight of foundation): 180 kN 

In addition, 3 boreholes have been sunk at the locations shown on the Site Plan and the logs of these boreholes are included in this brief.

REQUIRED TASKS TO BE CUNDUCTED

You are required to prepare a brief report to address the following aspects:

1. Find the consistency of the soil layers based on SPT N-values and provide a cross section of the ground layers of the site based on the information given in 3 borehole logs, which are attached in this document. Clearly show the bedrock and groundwater level positions.  (5%)

2. Based on the AS 4678 requirements, provide geotechnical design aspects of an anchored retaining wall that should be employed between the proposed building and the water tank. This should include sufficient results to enable the structural engineer to design the wall section, including the embedment depth, the minimum free length of the anchors, the anchor tensile force (assume the anchors spacing is 2 m) and the maximum moment of the wall per metre run that can be induced in the retaining structure. Assume position of the anchor is 1.8 m below the ground surface and the angle of the anchor is 15 degrees. (15%)

3. Design the width of the wall foundation (only a typical strip footing), the column footings (only a typical square footing) and the diameter of the water tank circular foundation. (15%)

4. Estimate settlements of the wall, column and water tank footings. Assume the average drained Poisson’s ratio of the soil is 0.30 and use the following formula to calculate the soils drained Young’s modulus in kPa: Es = 800 (N+13). (15%)

5. Using the method of slices, analyse the slope stability for the site south access batter and find the design slope angle to satisfy the required factor of safety of 1.6 ± 0.05.

Assume the height of slope is H1 = 3.6 m and the heigh of bottom sand layer is H2 = 5 m as shown in the figure. Appy a minimum surcharge of 5 kPa. Assume water depth is 5.5 m from the top of the slope. Solve this question for two different scenarios.  

Scenario 1 (use compacted sand for top layer): Assume the effective friction angle of stabilised soil is 32°, the total unit weight of soil is 19 kN/m3 and the effective cohesion of the stabilised soil is 1 kPa.

Scenario 2 (use cement stabilised sand for top layer): Assume the effective friction angle of stabilised soil is 36°, the total unit weight of soil is 20 kN/m3 and the effective cohesion of the stabilised soil is 8 kPa.

Bottom sand layer: Assume the effective friction angle of sand is 30°, the total unit weight of soil is 18 kN/m3 and the effective cohesion of the stabilised soil is 1 kPa.

You need to copy and paste at least 4 trials for each scenario to find the desired angle. (20%)

Guidelines:

You can use : Free Online Slope Stability Analysis for factor of safety.

https://calcforge.com/1/2/free-slope-stability-calculator

Or use Slope/W a module of Geo-Studio software and apply Morgenstern-Price or Spencer limit equilibrium method.

6. Employ three generative AI tools, including ChatGPT, Google Gemini, and Microsoft Copilot to find the answers to following questions, separately. You need to ask powerful follow-up questions from these generative AIs to enhance the answers. Please copy and paste your prompts and the GenAI responses for each AI tool. Then provide a reflective report (not more than one page) based on the generated responses and compare them with you own answers based on materials provided in this subject. (20%)

· Outline the recommended sequence of construction activities for this site.

· Provide a detailed list of recommendations for any additional field soil exploration necessary to finalize the design. Be specific; for instance, if additional boreholes are required, indicate the suggested quantity, precise locations, and recommended depths.

· List the essential laboratory tests needed and explain the purpose of each, specifying how they contribute to the design process.

The report should comprehensively address all the above aspects, including the associated workings and detailed calculations. The report must include a Title Page, Executive Summary of the main findings, Table of Contents, Project Scope, Detailed Calculations, and Results for all six outlined sections, along with a References list. Ensure all figures and tables are properly numbered and titled. If any figures or tables are sourced from external references, please provide appropriate citations or acknowledgments. (10%)

Note: The design of car park foundation and pavement, the design of retaining wall between the proposed building and the existing building, the design of retaining wall between the proposed building and the proposed car park, and landscape design are excluded in this design project.  

SUBMISSION

Submission date for your report is given in Canvas.

Each group will prepare only one report and one MS-Excel file, writing the names of both team members. However, each team member should individually submit that report.  

The Report as a pdf file and Calculations as an Excel file should be submitted via Canvas link.

  


热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图