代写COMP507- ITPM Semester 1 2024 ASSIGNMENT #2代写留学生Matlab语言程序

COMP507- ITPM

Semester 1 2024

ASSIGNMENT #2 (100 marks)

Contribution to final marks: 50%

Must get a minimum of 35/100 marks in this assignment to get an overall pass for this paper

Submission Requirements:

· This is an individual assignment. The cover page must have your ID number and Name (in full)

· Please use 1.5-line spacing and 12-point font (no handwritten assignment will be marked except for drawing the AOA diagram)

· Include page numbers.

Task1: Project Cost Control (30 marks)

You are required to control the budget for the MYH project. Below is the Business Case of the project.

Table 1

Business Case for MYH


1.1 What is the total budget at completion (BAC) for the project? (3 marks)

Assume that the work for the first week is completed in the project. The following information has been provided as a result of work done so far.

Plan Value (PV) = $400, 000

Earned Value (EV) = $250, 000

Actual Cost (AC) = $600, 000

Answer the following questions (1.2 – 1.6). You must show all the workings to support your answers.

1.2 Explain a likely reason for the difference between PV and AC for the first week of this project. (5 marks)

1.3 Calculate the cost variance (CV) and the cost performance index (CPI) for the first week of this project. Is the project under or over budget? (7 marks)

1.4 Calculate the schedule variance (SV) and the schedule performance index (SPI) for the first week of this project. Is the project ahead of or behind schedule? (7 marks)

1.5 Calculate the new estimate at completion (EAC) for this project after the completion of the first week’s work. (4 marks)

1.6 Calculate how long it will now take to finish this project after working on the project for a week. (4 marks)

Task 2: Project schedule development (35 marks)

Table 2 shown below provides the activities (A to L) and their three-point estimates for an Auckland City IT Infrastructure (LAN Network) project.

Table 2

Activities Schedule for Auckland City IT Infrastructure Project

Task

Predecessor

Optimistic duration (Day)

Most Likely duration (Day)

Pessimistic duration (Day)

Task effort

A

-

12

14

26

B

-

14

18

24

C

A

21

23

32

D

A

12

17

26

E

C

11

13

16

F

D

16

19

21

G

B

8

6

11

H

B

6

4

12

I

E, F, G

8

6

13

J

H

8

7

16

K

J

9

7

13

L

I, K

10

8

12

3.1 Complete the PERT estimation to show the duration of each activity. (10 marks)

3.2 Draw the network diagram (AOA) to show the order in which all the activities will be undertaken in this project. The diagram must be clearly labelled. (5 marks)

3.3 List all the possible paths for this project with their total durations. (4 marks)

3.4 Clearly identify and briefly explain the critical path for this project. (10 marks)

3.5 This network is expected to be up and running within 4 months from the time the work on the project is started. Does this opening date appear feasible? Justify with your calculations. (6 marks)

Task 3:  Project selection (15 marks)

You are required to perform. analysis to help identify the order in which the projects will be undertaken from the available four projects.

3.1 Use the information below to create a table that must show the weighted score and priority for each project for a software vendor environment. (10 marks)

The factors that impact the success of a project include (a) the availability of  a principal engineer (20%); (b) a development team assigned based on at least 4 senior software engineers with local development experience (20%);  (c) availability of a product manager as an on-site customer) (20%); (d) support for the project from the sales and marketing team (20%); (e) availability of an agile tester (10%); and (f) an established product backlog based on high-level requirements (10%).

Table 3 below provides the scores based on these factors for each project.

Table 3

Criteria for Projects 1-4

Project / Criteria

a

b

c

d

e

f

Project 1

65

45

45

60

55

60

Project 2

70

65

55

65

85

70

Project 3

75

70

75

75

85

50

Project 4

60

70

75

75

85

70

3.2 Explain the order in which these 4 projects should be undertaken. Justify with your calculations. (5 marks)

Task 4:  Project selection (20 marks)

4.1 Based on the information provided below, perform. a quantitative risk analysis using a decision tree diagram to calculate the expected monetary value (EMV) and contingency reserve for each project. (10 marks)

Project

Risks

Chance of Outcome

Estimated Impact

Expected monetary value (EMV)

Contingency reserve

Project 1

Risk 1

40%

-$ 60,000

Risk 2

60%

-$ 70,000

Project 2


Risk 1

20%

-$ 100,000

Risk 2

25%

$ 60,000

Risk 3

55%

$ 80,000

Project 3


Risk 1

20%

$ 60,000

Risk 2

25%

$ 75,000

Risk 3

55%

-$ 30,000

Project 4


Risk 1

40%

$ 60,000

Risk 2

35%

$ 40,000

Risk 3

25%

-$ 80,000

4.4 Explain the contingency reserve for each project. Justify with your calculations. (10 marks)


热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图