CE 574: Construction Means & Methods Final Exam

Project Execution Plan Team Presentation: 12/17, 4:30 PM via Zoom

SECTION 1.0 - PROJECT INFORMATION

This section of the Project Execution Plan is intended to provide the basic pertinent project information.

Project Information

Name:

Address:

Team Members:

Project Details: Provide a brief description of the project scope and size including but not limited to Product type, Gross SF, Lot size, Building footprint, number of stories, number of units (if applicable), number of parking stalls, etc.

SECTION 2.0 - SITE ANALYSIS

This section of the Project Execution Plan addresses specific site restrictions and challenges for the project site and its surrounding areas. A Site Logistics Plan along with a narrative should be included as part of this section. The Logistics Plan and/or narrative should address the following items at a minimum

Site Constraints & Neighboring Properties: Illustrate and discuss the proposed site access plan and identify any site constraints on-site and/or at surrounding properties. Examples of site conditions/constraints may include power lines, easements, and adjacent structures.

Traffic Plan/Street Closures: The Site Logistics Plan to be submitted as part of this plan should identify site access, traffic restrictions, and proposed street and sidewalk closures. Discuss the traffic closure strategy and potential costs associated with the closures. Identify sidewalk protection, fencing, K-rail, and overhead canopy requirements.

Haul Route: Prior to the award of the grading scope of work, identify if a haul route is required for the project. Verify if the project falls under the hillside requirements for haul routes, and haul route approvals.

Hoisting Strategy: Prepare a hoisting plan that identifies a hoisting strategy for the entire project. Include a logistics plan of the tower crane layout and elevations. Include one crane assist plan for erection and dismantle of one tower crane – assume a 500-ton mobile crane will do the job.

SECTION 3.1 - CONCRETE LOGISTICS

This section of the Project Execution Plan addresses the specific project site related challenges and the Team’s overall management approach to the project. The plan should breakdown the scope of work by concrete work areas and address the following:

Concrete Pours Breakdown & Sequence: For Building 2 only, provide floor plans with pour breaks, construction joints, SF and CY per pour, deck cycles if applicable, etc. Should present a clear sequence of how the concrete work will be executed including an explanation of the constraints and reasons for the sequencing. The pour sequencing plans should include decks only.

Concrete Deck Formwork Sequence: For Buildings 1, 2, 5, 6, and 7, identify how the deck formwork system will be cycled throughout this half of the project. Assuming $0.70/sf for deck formwork rental and $0.20/sf for deck reshoring rental (three floors of reshoring required at all “wet deck” shoring), estimate the total rental cost for deck formwork and reshoring.

SECTION 3.2 – STRUCTURAL STEEL LOGISTICS

The plan should breakdown the scope of work by steel work areas and address the following:

Structural Steel Building Areas & Sequence: Identify in plan the structural steel to be erected. Discuss hoisting concerns, access, and how these areas will be sequenced with the concrete structure. Your explanation should include highlighted areas of steel vs. concrete with schedule dates clearly identified and tying back to overall project schedule, ensuring the workforce is kept safe at all times.

SECTION 4.0 - PROJECT SCHEDULE & SEQUENCING PLAN

This section of the Project Execution Plan addresses the project schedule and sequencing plan for the project. The intent of the schedule plan is to identify critical project milestones and identify the potential time driven risks that can potentially impact the efficient completion of the work. The subject plan should convey the Team’s plan for sequence and flow of the work to allow for coordination of all the trades and manpower management of self- performed labor.

Building Turnover Plan. Complete a sequencing map to illustrate the start and finish dates of each building. Be sure to take into consideration the use of the building and your expectation of when the client will need to occupy the building. Use any of the following sheets to complete this exercise: A1.01, A1.02, A1.09.

Schedule. The Project Team shall prepare and submit Schedule identifying sequence, workflow and duration of critical work activities. The Schedule must illustrate the conceptualized critical path for the work and identify key milestone activities and dates for the project. The Schedule must provide sufficient detail appropriate to the size and complexity of the project.

SECTION 5.0 - INNOVATION STRATEGY

This section of the Project Execution Plan outlines the Team’s innovation strategy for the project.

Innovation Narrative. As part of this section include a brief narrative outlining the Team’s goal of implementing a new technology to assist in construction means and methods. Describe the problem you are solving and quantify the expected cost savings or risk management advantage associated to the innovation. List one KPI that you will use to quantifiably measure success.



热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图