BPLN0025: Business Cases for Infrastructure

MSc Infrastructure Planning, Appraisal and Development (IPAD)

Programme Examinations – May 2023

Time allowed/suggested time allowance: 2.0 hours

Wordcount: 2500 words

.    Answer THREE questions from PART A and ALL of PART B.

.    Part A attracts 60% of the overall marks, while Part B attracts 40% of the overall mark.

.    Use illustrations and include diagrams in your answers where they assist in providing explanation.

PART A: (60% of marks)

Answer THREE questions ONLY from Part A

Question 1

Discuss the rationale for developing an infrastructure business case, and the motivation behind the adoption of the ‘5-case model’ as specified in the HMT Green Book for government spending. (12% of marks)

Which of the 5 dimensions of this model has been typically seen as the most important by

HMT, and how reasonable is this focus given the multiple challenges of sustainable development? (8% of marks)

Question 2

Discuss the rationale of a Social Cost Benefit Analysis and briefly outline the stages of a typical Social CBA. (13% of marks)

Cost benefit analysis and multi-criteria analysis are examples of rational decision-making paradigms. Outline the strengths  and weaknesses of such paradigms when applied to infrastructure  decision making. Use a major infrastructure project to illustrate  your response. (7% of marks)

Question 3

Critically discuss the HM Treasury ‘Options Framework’ guidance for the longlisting and shortlisting  of  project  options.     Use  a  major  infrastructure  project  to  illustrate  your response. (20% of marks)

Question 4

Critically evaluate the approach and methods for risk identification and sharing specified by the HMT 5 case model (8% of marks)

Discuss whether the private sector involvement in infrastructure development, especially in partnership with the public sector, provides better outcomes than a traditional public sector approach? Use some examples of major infrastructure projects to illustrate your answer. (12% of marks)

Question 5

Briefly discuss the contingent valuation method for estimating economic prices for use in Cost Benefit Analysis.  Outline the typical applications, strengths and weaknesses of the methodology. (20% of marks)

Question 6

Explain the utility of cost benefit analysis for including issues of spatial and temporal equity into  the  decision-making  process.  Illustrate  your  response  with  reference  to  a  major infrastructure project of your choice. (20% of marks)

PART B: (40 per cent of marks)

You must answer ALL of Part B (questions, 7 8 and 9)

You  have  been  commissioned  by the  Department for Transport  (the ‘client’) to  assess elements of the strategic outline case for the ‘A303 Stonehenge Improvement Scheme’ . The A303 is a trunk road which provides the most direct route between London and South West England (Figure 1). The £1.8bn project proposes to upgrade a congested section of the existing A303 to dual carriageway and includes a 3.3km road tunnel (Figures 2 and 3) to help protect the Stonehenge, Avebury and Associated Sites World Heritage Site (WHS).

Figure 1: Photo of existing A303 single carriageway and WHS site

 

Figure 2: Architect’s drawing of planned 3.3 km tunnel included in the A303 Improvement Scheme

 

At its closest point the existing A303 passes within 165 metres of the Stonehenge monument and creates highly intrusive sights and sounds of traffic, detracting from an ideally tranquil rural setting for the Stones. The existing A303 runs through the heart of the WHS dividing it in two. This impacts on people’s experience and understanding of the WHS, by limiting the safe mobility of visitors and opportunities to explore the area south of the A303. Stonehenge is an important economic asset in its own right, both in respect of its iconic status and the 1.3 million visitors it attracts each year.

Figure 3: Map showing the location of the proposed improvement scheme route and tunnel

 

The A303 is recognised as a strategic route to the South West. Enhancing this corridor is expected to deliver region-wide economic benefits by improving regional connectivity, facilitating planned growth in housing and jobs, and by improving the perceptions of tourists who use the A303 to travel to the region.

The objectives of the Project are:

.    Transport – To create a high-quality route that resolves current and predicted

traffic problems and contributes towards the creation of an Expressway between London and the South West.

.    Economic growth – In combination with other schemes on the route, to enable growth in jobs and housing by providing a free flowing and reliable connection  between the East and the South West peninsula.

.    Cultural heritage – To contribute to the conservation and enhancement of the WHS by improving access both within and to the site.

.    Environment and community – To contribute to the enhancement of the historic  landscape within the WHS, to improve biodiversity along the route and to provide a positive legacy to communities adjoining the road.

Question 7

Evaluate the project spending objectives for the new crossing against the HMT SMART objectives framework. (8% of marks)

Question 8

The time scale for the construction of the project is 3 years, the subsequent operational life of the project is set as 7 years, with annual maintenance costs being incurred over this period.

Assuming the typically monetised transport benefits are expected to be:

.    travel time savings to motorists using the upgraded road,

.    accident cost savings arising from the higher design standards of the new road,

.    vehicle operating cost savings due to higher traveling speeds attainable on the new road,

.    Noise and air quality improvements from reduced congestion and below grade road surface.

Use the data outlined in table 1, 2 and 3 below to determine the economic return from the proposed scheme using the following indicators:

.    Net Present Value

.    Benefit/Cost Ratio

State your recommendation for the funding of the project based on the economic return. (12% of marks)

Question 9

Given the objectives of the A303 Improvement Scheme and your responses to Question 7 and 8 above, advise the DfT on the possible limitations of using CBA to determine the overall viability of the A303 Project.   Include in your discussion any other impacts which you consider important to be included in the analysis. (20% of marks)

Table  1:  Data  required  for  economic  analysis  of  the  A303  Stonehenge  Improvement Scheme

Description

Data

Reduction     in      accident     rates      due     to

improvement project

0.5 accidents per 106 vehicle-kilometres

 

 

Average cost of an accident

£7500

 

 

Value of time saved per vehicle kilometre

£0.0183 per vehicle-kilometre

 

 

Noise   and   air-quality    improvements    per

vehicle kilometre

£0.0003 per vehicle-kilometre

 

 

Average   speed    increase   due   to    upgrade project (v)

40km per hour

 

 

Discount rate

5%

 

 

Average vehicle operating cost

=((2+25/v+0.00001v2 )/100)   £   per   km (where v is average speed increase due to upgrade project)

Table 2: Costs and flows for each year of the operation of the road

Year

Predicted Flow

(106 veh-km/year)

Construction      cost

(£)

Operating cost

(£)

1

-

600,000,000

 

2

-

600,000,000

 

3

-

600,000,000

 

4

7000

 

12,000,000

5

7100

 

12,000,000

6

7200

 

12,000,000

7

7300

 

12,000,000

8

7400

 

12,000,000

9

7500

 

12,000,000

10

7600

 

12,000,000

Table 3: Discount factors

 



热门主题

课程名

omp9727 ddes9903 mgt253 fc021 int2067/int5051 bsb151 babs2202 mis2002s phya21 18-213 cege0012 math39512 math38032 mech5125 mdia1002 cisc102 07 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 efim20036 mn-3503 comp9414 math21112 fins5568 comp4337 bcpm000028 info6030 inft6800 bcpm0054 comp(2041|9044) 110.807 bma0092 cs365 math20212 ce335 math2010 ec3450 comm1170 cenv6141 ftec5580 ecmt1010 csci-ua.0480-003 econ12-200 ectb60h3f cs247—assignment ib3960 tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 econ7230 msinm014/msing014/msing014b math2014 math350-real eec180 stat141b econ2101 fit2004 comp643 bu1002 cm2030 mn7182sr ectb60h3s ib2d30 ohss7000 fit3175 econ20120/econ30320 acct7104 compsci 369 math226 127.241 info1110 37007 math137a mgt4701 comm1180 fc300 ectb60h3 llp120 bio99 econ7030 csse2310/csse7231 comm1190 125.330 110.309 csc3100 bu1007 comp 636 qbus3600 compx222 stat437 kit317 hw1 ag942 fit3139 115.213 ipa61006 econ214 envm7512 6010acc fit4005 fins5542 slsp5360m 119729 cs148 hld-4267-r comp4002/gam cava1001 or4023 cosc2758/cosc2938 cse140 fu010055 csci410 finc3017 comp9417 fsc60504 24309 bsys702 mgec61 cive9831m pubh5010 5bus1037 info90004 p6769 bsan3209 plana4310 caes1000 econ0060 ap/adms4540 ast101h5f plan6392 625.609.81 csmai21 fnce6012 misy262 ifb106tc csci910 502it comp603/ense600 4035 csca08 8iar101 bsd131 msci242l csci 4261 elec51020 blaw1002 ec3044 acct40115 csi2108–cryptographic 158225 7014mhr econ60822 ecn302 philo225-24a acst2001 fit9132 comp1117b ad654 comp3221 st332 cs170 econ0033 engr228-digital law-10027u fit5057 ve311 sle210 n1608 msim3101 badp2003 mth002 6012acc 072243a 3809ict amath 483 ifn556 cven4051 2024 comp9024 158.739-2024 comp 3023 ecs122a com63004 bms5021 comp1028
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图