PJM5900 70573 Foundations of Project Mgt

Individual Assignment 3 (Lab 2) is a continuation of Lab 1, where you began developing your project baseline. In this lab, you will further refine your project management skills by creating a detailed project schedule using Microsoft Project or ProjectLibre. The assignment involves switching all project activities to Auto Schedule, estimating and entering activity durations, adding task notes to document estimating techniques, and incorporating milestones. You will also define task relationships, including start-to-start and finish-tofinish dependencies, and incorporate lead and lag times. Additionally, you will add constraints and deadline reminders, display the critical path, and save your project in a Network Diagram view. This comprehensive exercise aims to enhance your proficiency in project scheduling and prepares you for developing a complete Performance Measurement Baseline (PMB) in Lab 3.

1. Implement all revisions suggested from the review of your previous lab submission. Resubmitting a file with the same mistakes will affect your score. (2 points)

2. Switch to Auto Schedule:

Ensure all your project activities are set to Auto Schedule. No tasks should be manually scheduled. (2 points)

3. Estimate and Enter Durations:

Estimate and enter durations for all your project activities. Consider the skill level required to perform. the task and resource availability when estimating activity durations. (3 points)

4. Add Task Notes:

Add task notes to at least two of your project activities to document your estimating techniques. Specify if you used PERT estimates, learning curves, expert judgment, or historical data, and explain why. (Hint: You can enter and review task notes on the Notes tab in the Task Information dialog box). (4 points)

5. Add Milestones:

Add at least three milestones to your project where they are most appropriate. (Hint: A milestone is an activity with zero cost and zero duration used in the schedule to indicate significant events within the plan, such as design completion or permit receipt). (5 points)

6. Add Task Relationships:

Add task relationships to all your project activities and milestones. Ensure that all activities have a predecessor, except the first one, and a successor, except the last one. Do not link summary tasks or work packages—only activities and milestones. If a work package has not been broken down into activities, it should have a predecessor and a successor. (5 points)

7. Add Start-to-Start and Finish-to-Finish Relationships:

Add a start-to-start relationship between two pairs of project activities that should be planned in parallel. Add a task note explaining why these activities should be done in parallel instead of in sequence. Additionally, add a finish-to-finish relationship to two project activities and include a task note explaining why these activities should be planned this way. (3 points)

8. Add Lead Time:

Add lead time to at least one task relationship. (Hint: In MS Project, lead time is entered as a negative lag). (2 points)

9. Add Lag Time:

Add lag time to at least one task relationship. (2 points)

10. Add Constraints:

Add a constraint to one activity. For any task that has been constrained, add a comment explaining why it is constrained. (2 points)

11. Add a Deadline Reminder:

Add a deadline reminder to at least one task or milestone. (2 points)

12. Display the Critical Path:

Display the critical path of your project schedule and ensure that some activities have slack time. Not all activities should be on the critical path. (5 points)

13. Save as Network Diagram View:

Display your project in a Network Diagram view and save it so that it automatically opens in that view. (3 points)

Important Notes:

Your project file should include at least 50 lines of deliverables, work packages, and activities.

Remember that planning is an iterative process. You can revise your plan as more information becomes availale.

Your project activities must be original. Do not copy information from other sources. Assignments that are not original will receive a zero score.

Review the attached file to understand how to structure your deliverables, work packages, and activities.

This assignment tests your understanding of the difference between project deliverables and activities. Do not enter any information other than what is required for the assignment (e.g., do not enter activity duration or resources). The schedule and budget for your project will be completed progressively.

Microsoft Project Training Resources are available in Canvas > Modules > Microsoft Project Resources.





热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图