VQB5642: PERFORMANCE CODES METHODOLOGY & STRUCTURE

WEEK 6: Practice Case Study Assignment

General Guidance

Answer the question. Look exactly at what is asked. Don’t just write down everything you know.

Try to put yourself in the position of an assessor – you aren’t designing you are assessing

Don’t take any reference or calculation on the face value – check it

Question 1

(Mainly what is given / you can infer, rather than what should be given)

1. < 25m (lesser DtS requirement)

2. 4 storey (not 5) and atrium connecting all floors

3. Sprinkler protected

4. City block bounded on 2 sides

5. Egress via atria (internal discharge)

6. Office occupants familiar with the building

7. Occupants alert and mobile

8. Return air via atrium (possibility of smoke/flame spread)

9. Separate occupancies and movement only via balcony – possible entrapment if fire b/w office and stair

10. Atrium – results in enhanced smoke production

11. Service shafts connecting all floors (smoke spread)

12.Occupants on ground floor may not be familiar

13.Visual access to atrium through glazed partitioning (fire cue, visibility etc.)

Part B (basically, in light with IFEG sections 1.2.3 and 1.2.4)

1. No description of type of structure

2. No description of people and characteristics (% of mobility impaired)

3. No mention of inter-relationships of the offices or possible layouts

4. No discussion of after hours

5. No description of fire systems to be installed or location

6. No mention of management systems such as EWIS, building alarm, floor wardens

Question 2

1. Non-compliance with DtS should be identified and clarified with BCA performance requirements.

2. Need more specific description of FRL for fire resistance

3. NO justification is given why two stairs can be used in lieu of three for evacuating.

4. NO information about exit door size, evacuation plan…

5. NO mention of evacuation strategy

6. Only beam detectors at the roof of atrium has been mentioned. What’s about other location (office, cafe)?

7. Need more specific description of using fire safety system like Fire hydrant, Fire extinguisher, Smoke Alarm…

8. Hazard analysis should have been conducted before suggesting trial designs.

Question 3

1. Performance clauses not given, only functional statements.

2. Functional statements are at guidance level, compliance level is performance requirement.

3. Non-compliance with DtS should have been identified and should be related back to the performance requirements.

4.Totally wrong interpretation of the BCA and the relationship between Objectives, Functional Statements, Performance Requirements and DTS.

Question 4

1. It is mentioned that design should be such that the occupants can avoid untenable conditions. A clear fire safety strategy of “every one out” should be stated.

2. The approach is - whether quantitative/qualitative, comparative/absolute, deterministic/probabilistic - not mentioned

3. Should explain Acceptance Criteria clearly - whether ASET vs RSET or ERL, etc.

4. Sensitivity / redundancy / factor of safety is not proposed

5. No information about Purser and Bryan

6. No mention of Fire Brigade Personnel Tenability Criteria

Question 5

1. Inadequate design fires and locations. No justification of 5MW or relation back to fuel load configuration, e.g. horizontal spread.

2. “In the offices, the fire will not be analysed since the office part of the building is not being dealt with by performance methods.” - unacceptable logic.

3. Ignores fire in offices and spill plumes and fires located closer to higher level floors.

4. No mention of sprinkler effectiveness.

5. No sprinkler failure scenarios or basis for accepting only sprinklered solution.

6. Relates smoke properties to fuel which is good

7. No information on Tewarson.

Question 6

1. Design fires and scenarios incomplete and confused

2. No information on QUICKFIRE (CFD or zone model) and its capability

3. Does not mention time to untenable conditions

4. No equation for optical density and CO concentration is given

5. No consideration of possible smoke movement into non-pressurised stairs

Question 7

1. Considers fire spread from atrium to offices not other way. What is likelihood of fire in offices and the associated fire sizes? Glass temp will not reach 240oC not shown.

2. Office fire may result in a larger fire due to radiation feedback.

3. No justification of 6m diameter. Should relate 5MW back to HRR/area or other basis.

4. Agree with external flame spread scenario via external vs internal. However, windows breaking may lead to very large fire, lead to breaking tempered glass separating atrium/office

Question 8

1. Good justification of why not using IFEG

2. Ignores evacuation through atrium even though people have to travel through atrium

3. Does not consider possible entrapment of one office part on a level

4. 6.5 minute response and coping time appears large

5. No calculation provided to show beam detector activation occurs 1 minute after the fire has started

6. Assumes both stairs are available

7. No information on Pauls.

8. No mention of training on EWIS

9. Has ignored people in café

10. No account taken of possible visitors / disabled persons

11. Is 10.5 min enough to avoid untenable condition? Only up to 5 min calculation is shown in Table 9.1

Question 9

1. Design fire not developed logically – including the size and locations

2. Sensitivity analysis

3. Not clear approach, method of analysis and acceptance criteria

4. Evacuation time is 10.5 min, tenability is shown up to 5 min.

5. Inadequate justification of model used/ inadequate referencing

6. Performance requirements to be set out.

7. Overall fire-safety strategy needs to be explained, i.e. how are the performance requirements to be met.

8. Many more….




热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图