代写AP/ADMS 3353 Section A and B Project Management – Fall 2024 ASSIGNMENT-1代做留学生Matlab编程

AP/ADMS 3353 Section A and B

Project Management – Fall 2024

ASSIGNMENT-1

Due date : Friday, October 11, 2024 till 10:00 am)

Question # 1

Instructions:    There are four parts to this question. Don't start any part in the middle of the page.

Start each part on a new page.

Part – A)

(A-1)   Briefly describe the functional project management structure.

(A-2)   What are the relative advantages and disadvantages of the matrix, and dedicated team approaches to managing projects?

Note1:    Part-A should not be less than one and half pages and not more than two and half pages with single line spacing. Margins 1 inch in all corners, Font size 12)

Part B)

List all elements of a typical scope statement and then briefly describe them. Write any three complete project objectives.

Note1:    Part-B should not be less than (1.5) one and a half pages and not more than (2.5) two and a half pages with single line spacing. Margins 1 inch in all corners, Font size 12)

Part C)

How is culture created and communicated in organizations? Pick one organization like Microsoft, TTC, etc. and discuss their culture.

(Note1:   Part-C should not be less than two pages and not more than four pages with single line spacing. Margins 1 inch in all corners, Font size 12)

Note2: You are NOT allowed to pick ``Google`` as an organization to discuss its culture.

Note3: First, discuss briefly about the organization and then its culture. The major part must cover the culture of the organization.

Part D) [This part has no link with Part-C answer independently]

Do the research work to find projects which are completed or in process.

(D-1)   First, list three projects that have been completed and two projects that are in progress.

(D-2)   For all five projects listed in part D-1, briefly discuss (at least) their scope, duration, and budget independently.

(Note:    Do not mix D-1 and D-2, label your answers appropriately. Part-D should not be less than two pages and not more than four pages with single line spacing. Margins 1 inch in all corners, Font size 12)

QUESTION 2

Mr. John and his wife, Nancy, are planning their new house. The house's lot is in a small county's newly developed area. The plans show the house size to be 225 square yards, equal to 2025 square feet. The average price for a lot and house similar to this one has been $475 per square foot. Fortunately, Mr. John is a handy person working with a property and home maintenance company and feels he can save money by performing Furnace installed and plumbing fixtures himself. Nancy feels she can take care of the interior decorating.

The following average cost information is available from a local bank that loans local contractors and disperses progress payments to contractors when specific tasks are verified as completed.

22.10%

Excavation and framing complete

9.85%

Roof and fireplace completed

3.15%

Wiring roughed in

4.25%

Plumbing roughed in

3.50%

Siding on

16.35%

Windows, insulation, walks, plaster, and garage complete

2.15%

Furnace installed

2.65%

Plumbing fixtures installed

8.25%

Exterior paint

3.85%

Light fixtures installed

7.25%

Finish hardware installed

6.05%

Carpet and trim installed

4.85%

Interior decorating

5.75%

Floors laid and finished

a.   What is the estimated cost for John's house if they use contractors to complete the entire house? Must show the cost breakdown for each task.

b.   Estimate the amount to be paid to the contractor if John and his wife use their talents to complete some tasks themselves. Must show the revised cost breakdown for each task.

Note: Show support work. You may not get full marks if only the final answer is provided.

Note: This question is designed for testing purposes only.

Question # 3

Mega Master Public Company (MMPC) specializes in designing and assembling the agricultural drone. Top Farming Inc. (TFI) gave the first order to supply seven drones. MMPC produced and delivered these seven drones to TFI.

Four factors are involved: quality hours from the quality department, technical hours from the engineering department, electrical hours from the electrical department, and material and other costs. Learning varies for these factors, and there is no change in the material and other costs. The first drone took 42 hours from the engineering department, 30 hours from the electrical department and 21 hours from the quality department. Material and other costs for each drone are $1076 per drone. MMPC determined a learning rate of 80% in engineering department hours, 75% in electrical department hours and 90% in quality department hours. MMPC pay $40, $44, and $32 per hour to their engineering, electrical, and quality workers, respectively.

Top Farming Inc. placed a second order for nine drones immediately after receiving the first order. They were satisfied with the performance of the drones and placed a third order for fourteen drones. Learning in all three departments' hours continues, and the MMPC pay rate, material and other costs have not changed. MMPC completed and delivered all orders to TFI.

(a) What would be the average cost of a unit in the third order?

(b) What was the cost of the 9th  unit of the third order?

(c) TFI contacted MMPC to place a fourth order for 40 more drones. Now, the pay rates in all departments of MMPC increased by 8.25%, and material and other costs increased by $364.

(c-i)     Assume that the conditions are totally in MMPC's favor, which means the

learning continues in all three departments. What would be the total cost of this fourth order?

(c-ii)    Assume that conditions are totally in MMPC's favor, which means the learning  continues in all three departments. What would be the cost of the 15th  drone of this fourth order?

(c-iii)   Suppose there was a significant delay between the third and fourth orders.

Assume that conditions are not in MMPC's favor, which means the learning achieved by completing the previous orders didn't continue. What would be the total cost of this fourth order?

Question # 4

Minerva Gonzales, project manager of Rising Fabricating Company (RFC), wants you to prepare a project network (AON) and answer questions. Her team determined the activities required to complete the project, the precedence relationship, and activity times as follows:

ID

Immediate Predecessor/s

Time (days)

A

None

5

B

A

7

C

B

5

D

None

7

E

B, D

6

F

None

8

G

D

12

H

A, F

6

I

E

4

J

H

4

K

C, E

2

L

I

4

M

J, K

4

N

J, K

5

O

L, N

3

P

G, I, K

6

Answer the following questions:

a.  Draw the network for the above project, compute each activity's early, late, and slack

times, and mark the critical path/s on the network. Must use the given legend of the node. Must include start and finish node.

b.  Which activities are critical, state all?

c.  What is the project completion time in days?

d.  What is/are the critical path/s for the above project? State them?

e.  Which activity/ies is/are burst activity/ies?

f.   Which activity/ies is/are having properties of 'merge and burst' activity/ies?

g.  How many paths are available in the network?

h.  Draw the GANTT chart of the project.

i.    If there is a delay in the completion of activity 'G' by two days, what impact will be on project completion time and critical path/s? Briefly explain. (No link with parts 'j or k')

j.    If activity 'H' took an extra day to complete, what impact will be on project completion time and critical path/s? Briefly explain. (No link with parts 'i or k')

k.   If activity 'L' is completed a day earlier than the estimated time, what impact will be on project completion time and critical path/s? Briefly explain. (No link with part 'i or j')

Note: when drawing, the network must use the following Node Legend. The diagram must be in the appropriate size. The page where you drew network diagram, no other work should be presented. Network diagram must be in the

Landscape form. of the page.

Legend

ES

ID

EF

SL

LS

DUR

LF




热门主题

课程名

mktg2509 csci 2600 38170 lng302 csse3010 phas3226 77938 arch1162 engn4536/engn6536 acx5903 comp151101 phl245 cse12 comp9312 stat3016/6016 phas0038 comp2140 6qqmb312 xjco3011 rest0005 ematm0051 5qqmn219 lubs5062m eee8155 cege0100 eap033 artd1109 mat246 etc3430 ecmm462 mis102 inft6800 ddes9903 comp6521 comp9517 comp3331/9331 comp4337 comp6008 comp9414 bu.231.790.81 man00150m csb352h math1041 eengm4100 isys1002 08 6057cem mktg3504 mthm036 mtrx1701 mth3241 eeee3086 cmp-7038b cmp-7000a ints4010 econ2151 infs5710 fins5516 fin3309 fins5510 gsoe9340 math2007 math2036 soee5010 mark3088 infs3605 elec9714 comp2271 ma214 comp2211 infs3604 600426 sit254 acct3091 bbt405 msin0116 com107/com113 mark5826 sit120 comp9021 eco2101 eeen40700 cs253 ece3114 ecmm447 chns3000 math377 itd102 comp9444 comp(2041|9044) econ0060 econ7230 mgt001371 ecs-323 cs6250 mgdi60012 mdia2012 comm221001 comm5000 ma1008 engl642 econ241 com333 math367 mis201 nbs-7041x meek16104 econ2003 comm1190 mbas902 comp-1027 dpst1091 comp7315 eppd1033 m06 ee3025 msci231 bb113/bbs1063 fc709 comp3425 comp9417 econ42915 cb9101 math1102e chme0017 fc307 mkt60104 5522usst litr1-uc6201.200 ee1102 cosc2803 math39512 omp9727 int2067/int5051 bsb151 mgt253 fc021 babs2202 mis2002s phya21 18-213 cege0012 mdia1002 math38032 mech5125 07 cisc102 mgx3110 cs240 11175 fin3020s eco3420 ictten622 comp9727 cpt111 de114102d mgm320h5s bafi1019 math21112 efim20036 mn-3503 fins5568 110.807 bcpm000028 info6030 bma0092 bcpm0054 math20212 ce335 cs365 cenv6141 ftec5580 math2010 ec3450 comm1170 ecmt1010 csci-ua.0480-003 econ12-200 ib3960 ectb60h3f cs247—assignment tk3163 ics3u ib3j80 comp20008 comp9334 eppd1063 acct2343 cct109 isys1055/3412 math350-real math2014 eec180 stat141b econ2101 msinm014/msing014/msing014b fit2004 comp643 bu1002 cm2030
联系我们
EMail: 99515681@qq.com
QQ: 99515681
留学生作业帮-留学生的知心伴侣!
工作时间:08:00-21:00
python代写
微信客服:codinghelp
站长地图